Search found 103 matches

by RiseHigh
Sat Jul 01, 2017 7:41 pm
Forum: CBD Development
Topic: [COM] Adelaide Convention Centre - Stage 3 | $350m
Replies: 1462
Views: 496993

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

IMG_338.jpg IMG_337.jpg t A couple of pics from inside the new convention centre What's the reason for two bays of seats being on an opposite slope where you'd be sitting at a steep angle looking towards the roof? Is each bay moveable to adjust the seating and the available room? Obviously they hav...
by RiseHigh
Sat Jul 01, 2017 7:35 pm
Forum: CBD Development
Topic: [COM] Adelaide Convention Centre - Stage 3 | $350m
Replies: 1462
Views: 496993

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

As you can see from the previous pic under the seating trusses they have used optic fibre for a pretty impressive lighting display, it would look great when all the seats have been lifted and the main lights are dimmed or off.
by RiseHigh
Sat Jul 01, 2017 12:50 pm
Forum: CBD Development
Topic: [COM] Adelaide Convention Centre - Stage 3 | $350m
Replies: 1462
Views: 496993

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

IMG_338.jpg
IMG_338.jpg (152.34 KiB) Viewed 5543 times
IMG_337.jpg
IMG_337.jpg (128.26 KiB) Viewed 5543 times
t
A couple of pics from inside the new convention centre
by RiseHigh
Mon Jun 19, 2017 9:46 pm
Forum: CBD Development
Topic: [COM] Adelaide Convention Centre - Stage 3 | $350m
Replies: 1462
Views: 496993

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

IMG_0175.PNG
IMG_0175.PNG (1.43 MiB) Viewed 4706 times
In this photo you can see the seating turntables at the top, one is spun halfway round the other faceing the other way
by RiseHigh
Mon Jun 19, 2017 9:39 pm
Forum: CBD Development
Topic: [COM] Adelaide Convention Centre - Stage 3 | $350m
Replies: 1462
Views: 496993

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

IMG_0173.PNG
These seating trusses lift up and out of the way when needed
IMG_0173.PNG (1.5 MiB) Viewed 4711 times
by RiseHigh
Thu May 25, 2017 8:23 pm
Forum: CBD Development
Topic: [COM] Adelaide Convention Centre - Stage 3 | $350m
Replies: 1462
Views: 496993

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

IMG_0155.PNG
IMG_0155.PNG (2.66 MiB) Viewed 5431 times
by RiseHigh
Tue May 23, 2017 9:12 pm
Forum: CBD Development
Topic: [COM] Adelaide Convention Centre - Stage 3 | $350m
Replies: 1462
Views: 496993

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Sorry that pic didn't upload very well
by RiseHigh
Wed Aug 17, 2016 9:24 pm
Forum: CBD Development
Topic: [COM] 115 King William Street | 91m | 26lvls | Office
Replies: 656
Views: 227594

[COM] Re: 115 King William Street | 91m | 26lvls | Office

The elevator infront of the building that the workers have been using has been coming down. It goes up and down, it's an elevator. :banana: Very funny :lol: better choice of words would be that the elevator haa been dismantled and brought down to level 9 of the building. So it'll probably be gone a...
by RiseHigh
Mon Jun 27, 2016 8:27 pm
Forum: CBD Development
Topic: [COM] Adelaide Convention Centre - Stage 3 | $350m
Replies: 1462
Views: 496993

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

There is some interesting work happening at the moment on site they are building two large turntables with hundreds of seats on them that can turn around to view multiple stages, it's going to be pretty impressive when it's finished.
by RiseHigh
Mon Jun 20, 2016 8:29 pm
Forum: CBD Development
Topic: [COM] Adelaide Convention Centre - Stage 3 | $350m
Replies: 1462
Views: 496993

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

Completion is schedule for the second half of... next year? Surely they mean this year. It looks almost finished now. ...You're joking, right? Have a look at the photos above, they're yet to apply the final cladding on the Torrens end, the building is largely a skeleton on the North Terrace end and...
by RiseHigh
Mon Jun 13, 2016 10:36 pm
Forum: CBD Development
Topic: [COM] Adelaide Convention Centre - Stage 3 | $350m
Replies: 1462
Views: 496993

[COM] Re: Adelaide Convention Centre - Stage 3 | $350m

As soon as they close this site up that's when the progress will speed up, the noise is slowing progress with the hotel next door complaining. The plan is to get the walls and roof done then there will be extra shifts around the clock to get this site moving.
by RiseHigh
Mon Oct 27, 2014 8:53 pm
Forum: CBD Development
Topic: [COM] 413 KWS Vue on King William | 89m | 28Lvl | Residential
Replies: 1087
Views: 320394

[COM] Re: U/C: 413 KWS Vue on King William | 89m | 28Lvl | Residen

Briggzy_03 wrote:A friend who works as a cement truck driver told me that they're doing a huge delivery job for this development not this Saturday but the next.
My friend who is also a cement truck driver told me the same thing
by RiseHigh
Wed Sep 18, 2013 8:43 pm
Forum: CBD Development
Topic: [COM] SAHMRI | $200m
Replies: 615
Views: 180669

[COM] Re: U/C: SAHMRI | $200m

There are some great shots you could get if you work in this building like the centre foyer area near the glass lifts. If you stand on level nine and look down the centre foyer it looks very impressive, or stand on level 3 and look up the centre it's amazing how the facade supports itself. Those ph...
by RiseHigh
Mon Sep 16, 2013 9:33 pm
Forum: CBD Development
Topic: [COM] SAHMRI | $200m
Replies: 615
Views: 180669

[COM] Re: U/C: SAHMRI | $200m

There are some great shots you could get if you work in this building like the centre foyer area near the glass lifts. If you stand on level nine and look down the centre foyer it looks very impressive, or stand on level 3 and look up the centre it's amazing how the facade supports itself. Those pho...