Re: Crane Counter: CBD 13 | Metro 3| Total 16

Posted: Sat Mar 30, 2019 6:11 pm
by EBG
The market St crane is nearly complete except for stringing up some cables.at 5 pm Sat 30/3/2019. This crane was previously at the urbanest site in synagogue place.

Re: Crane Counter: CBD 13 | Metro 3| Total 16

Posted: Sat Mar 30, 2019 6:15 pm
by EBG
The U2 crane was still at the tower stage at 5 pm Sat 30/3/2019, with the rest of the crane beam assembled in Waymouth St on the ground.

Re: Crane Counter: CBD 13 | Metro 3| Total 16

Posted: Sat Mar 30, 2019 6:20 pm
by EBG
The Frome St crane has got the climbing frame attached near the top of the tower so it could gain in height very soon. 30/3/2019

Re: Crane Counter: CBD 13 | Metro 3| Total 16

Posted: Sun Mar 31, 2019 3:36 pm
by EBG
The U2 crane nearly complete.

Re: Crane Counter: CBD 13 | Metro 3| Total 16

Posted: Sun Mar 31, 2019 3:39 pm
by EBG
The Frome St crane has definitely gained height. Also the Realm lift core is just visible behind the student tower in Synagogue place. Click on picture for Bigger.

Re: Crane Counter: CBD 13 | Metro 3| Total 16

Posted: Sun Mar 31, 2019 4:46 pm
by phenom
This didn't work as well as I thought it would :roll: but was intended to show the deconstruct of the crane at UCity and the U2 reconstruct.
ucity-u2-craneswap.png

Re: Crane Counter: CBD 13 | Metro 3| Total 16

Posted: Sun Mar 31, 2019 4:48 pm
by phenom
Also: Market St crane on 31/3/2019
market street crane.jpg

Re: Crane Counter: CBD 13 | Metro 3| Total 16

Posted: Sun Mar 31, 2019 6:53 pm
by Smithy85
We all (me included) keep calling the Waymouth development “U2”. Isn’t it called something else now?

Re: Crane Counter: CBD 13 | Metro 3| Total 16

Posted: Sun Mar 31, 2019 7:31 pm
by Ben
Smithy85 wrote:
Sun Mar 31, 2019 6:53 pm
We all (me included) keep calling the Waymouth development “U2”. Isn’t it called something else now?
I believe its a hotel but no official press release yet.

Re: Crane Counter: CBD 14 | Metro 3| Total 17

Posted: Sun Mar 31, 2019 9:52 pm
by EBG
U2.2

Re: Crane Counter: CBD 14 | Metro 3| Total 17

Posted: Sat Apr 06, 2019 8:37 am
by Jaymz
While the number of CBD cranes hasn't really increased over the past couple of years, it's still encouraging to at least see them moving to a new project upon completion of a previous development.

When I was living in Adelaide during the mid to late 90's, I recall going for months, even a year or 2 without a single crane on the skyline.

Re: Crane Counter: CBD 14 | Metro 3| Total 17

Posted: Sat Apr 13, 2019 4:31 pm
by jackfire
Crane went up today in the vicinity of 248 South Terrace and student accommodation 89 Gray Street crane coming down.

Re: Crane Counter: CBD 14 | Metro 3| Total 17

Posted: Sat Apr 13, 2019 8:08 pm
by EBG
The Gray St crane is 1/2 down, the tower sections will come down tomorrow. The South Tce crane is in line with Glen Osmond Rd.

Re: Crane Counter: CBD 14 | Metro 3| Total 17

Posted: Sat Apr 13, 2019 10:40 pm
by EBG
This is a small apartment project consisting of Ground floor car park, 6 levels of apartments plus roof top BBQ area.

Re: Crane Counter: CBD 14 | Metro 3| Total 17

Posted: Sat Apr 13, 2019 10:59 pm
by EBG
252 South Tce. There is actually only one Large apartment per floor.