[COM] 295-297 Pirie Street | 60m | 16 Levels | Apartments

All high-rise, low-rise and street developments in the Adelaide and North Adelaide areas.
Post Reply
Message
Author
Tek Screw
Sen-Rookie-Sational
Posts: 17
Joined: Thu Jan 25, 2018 1:33 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#91 Post by Tek Screw » Tue Mar 27, 2018 12:07 pm

On the back of Smithy85: photo from The Advertiser - Sat 24/03/2018 attached.

I presume Built Environs won a bid to undertake the demolition works and level the building platau but were not able to secure the building contract.
That's a bit awkward...
Attachments
East End.jpg
East End Builder
East End.jpg (1.34 MiB) Viewed 8238 times

Ben
VIP Member
VIP Member
Posts: 7475
Joined: Mon Dec 19, 2005 11:46 am
Location: Adelaide

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#92 Post by Ben » Thu Apr 05, 2018 1:21 pm

Construction begins on an $80 million East End Apartment project in Adelaide CBD
Giuseppe Tauriello, The Advertiser

CONSTRUCTION of an $80 million apartment project in the East End has kicked off as CBD stamp duty concessions draw to a close.

Developer Wellstone Property says its East End Apartments project at the eastern end of Pirie St will create 350 jobs during construction.

Designed by local architect Cheesman Architects and to be built by Hindmarsh Construction, the project will add 140 apartments to the city skyline across 16 storeys.

Wellstone Property director Damon Semanic said more than half of the apartments were already sold, with demand boosted by the Adelaide City Council’s rates rebate to owner-occupiers, last year’s $10,000 pre-construction grant and off-the-plan stamp duty concessions, which end in June.

“East End Apartments is set to become a premier destination for modern inner city living in Adelaide, so we’re absolutely thrilled to turn the first sod and commence construction,” he said.

“Our development team has put in countless hours of design and planning work to get to this point, so it’s exciting to start turning our plans for the site into reality.”

The project includes one, two and three-bedroom apartments, with prices starting from $399,000 for two-bedroom floorplans.

Mr Semanic said stencil artworks would be painted on the exterior of the building by local artist Joshua Smith.

“The apartments themselves will also be immaculately appointed and feature glass-embraced

balconies, along with floor-to-ceiling windows to enhance the amazing views that will be available of the city, parklands and Adelaide Hills,” he said.

Planning Minister Stephan Knoll and Lord Mayor Martin Haese attended Thursday’s ceremony to officially break ground on the project.

The project is expected to be completed by the end of next year.

EBG
Super Size Scraper Poster!
Posts: 2930
Joined: Fri Jul 12, 2013 10:49 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#93 Post by EBG » Tue Apr 24, 2018 11:33 pm

Piling is now starting from the front ((Pirie St) side. Picture 24/4/2018.
Attachments
20180424_pirie 2.jpg
20180424_pirie 2.jpg (215.12 KiB) Viewed 7727 times
20180424_pirie 1.jpg
20180424_pirie 1.jpg (440.3 KiB) Viewed 7727 times

EBG
Super Size Scraper Poster!
Posts: 2930
Joined: Fri Jul 12, 2013 10:49 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#94 Post by EBG » Fri May 04, 2018 9:43 pm

4/5/2018 now piling at rear of site.
Attachments
20180504_pirie st 1.jpg
20180504_pirie st 1.jpg (194.35 KiB) Viewed 7500 times

Ben
VIP Member
VIP Member
Posts: 7475
Joined: Mon Dec 19, 2005 11:46 am
Location: Adelaide

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#95 Post by Ben » Tue May 29, 2018 12:17 pm

Crane base now on site.
Attachments
east end.jpg
east end.jpg (792.87 KiB) Viewed 7181 times

Ser Noit of Loit
High Rise Poster!
Posts: 224
Joined: Sun Feb 26, 2017 5:12 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#96 Post by Ser Noit of Loit » Tue May 29, 2018 7:28 pm

I saw this today too and took a picture to post here. You beat me to it though.

GrowAdelaide
High Rise Poster!
Posts: 290
Joined: Thu Jul 06, 2017 11:35 am

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#97 Post by GrowAdelaide » Wed May 30, 2018 1:46 pm

Ben wrote:
Tue May 29, 2018 12:17 pm
Crane base now on site.
Does anyone else think the placement of the crane odd? Is it going to grow out of a lift core?

Allkai
High Rise Poster!
Posts: 340
Joined: Thu Sep 04, 2008 12:59 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#98 Post by Allkai » Wed May 30, 2018 4:44 pm

GrowAdelaide wrote:
Wed May 30, 2018 1:46 pm
Ben wrote:
Tue May 29, 2018 12:17 pm
Crane base now on site.
Does anyone else think the placement of the crane odd? Is it going to grow out of a lift core?
Stair.

User avatar
timtam20292
Legendary Member!
Posts: 1384
Joined: Tue Apr 19, 2016 1:03 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#99 Post by timtam20292 » Wed May 30, 2018 4:46 pm

GrowAdelaide wrote:
Wed May 30, 2018 1:46 pm
Ben wrote:
Tue May 29, 2018 12:17 pm
Crane base now on site.
Does anyone else think the placement of the crane odd? Is it going to grow out of a lift core?
It's not uncommon, 115 King William Street's crane was in the core.

EBG
Super Size Scraper Poster!
Posts: 2930
Joined: Fri Jul 12, 2013 10:49 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#100 Post by EBG » Wed May 30, 2018 10:37 pm

Normally the crane would be as close to the centre of the site as possible. In this case as the crane is close to the front of the site,it means the crane will have to have a long reach to cover the back corners.

EBG
Super Size Scraper Poster!
Posts: 2930
Joined: Fri Jul 12, 2013 10:49 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#101 Post by EBG » Sun Jun 17, 2018 3:21 pm

A mobile crane installed some precast wall panels along rear part of the west side. picture 17/6/2018.
Attachments
20180617_pirie st.jpg
20180617_pirie st.jpg (322.14 KiB) Viewed 6381 times
Last edited by EBG on Sat Jun 23, 2018 9:28 pm, edited 1 time in total.

citywatcher
Legendary Member!
Posts: 862
Joined: Sun Jul 15, 2007 5:51 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#102 Post by citywatcher » Sat Jun 23, 2018 6:42 pm

Still no crane

Sent from my SM-J730G using Tapatalk


EBG
Super Size Scraper Poster!
Posts: 2930
Joined: Fri Jul 12, 2013 10:49 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#103 Post by EBG » Mon Jun 25, 2018 3:57 pm

More precast wall Panels installed by mobile. no tower crane yet. 25 June 18
Attachments
20180625_pirie st.jpg
20180625_pirie st.jpg (132.24 KiB) Viewed 5884 times

EBG
Super Size Scraper Poster!
Posts: 2930
Joined: Fri Jul 12, 2013 10:49 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#104 Post by EBG » Tue Jun 26, 2018 9:32 pm

The mobile crane also lifted some precast lift core panels in to place today 26/6/18.
Attachments
20180626_Pirie st.jpg
20180626_Pirie st.jpg (289.43 KiB) Viewed 5696 times

citywatcher
Legendary Member!
Posts: 862
Joined: Sun Jul 15, 2007 5:51 pm

[COM] Re: 295-297 Pirie Street | 60m | 16 Levels | Apartments

#105 Post by citywatcher » Thu Jul 05, 2018 8:06 am

Crane going up

Sent from my SM-J730G using Tapatalk


Post Reply

Who is online

Users browsing this forum: No registered users and 65 guests