[COM] M2 Northern Connector | 15.5km | $867m

Threads relating to transport, water, etc. within the CBD and Metropolitan area.
Message
Author
mawsonguy
High Rise Poster!
Posts: 196
Joined: Fri Dec 20, 2013 8:11 am

[COM] Re: PRO: Northern Connector | 14km | $1b

#461 Post by mawsonguy » Sun Jan 24, 2016 12:27 pm

Surely, something like this would be more practical? Passes over the rail line at a narrow point, utilises under-developed industrial land, does not disrupt existing roads and keeps the turns wide.

Image

User avatar
ChillyPhilly
Super Size Scraper Poster!
Posts: 2588
Joined: Sun Dec 07, 2008 11:35 pm
Location: Kaurna Land.
Contact:

[COM] Re: PRO: Northern Connector | 14km | $1b

#462 Post by ChillyPhilly » Mon Jan 25, 2016 4:35 am

That's basically the original MATS corridor.
Our state, our city, our future.

All views expressed on this forum are my own.

User avatar
drsmith
Legendary Member!
Posts: 513
Joined: Wed Nov 07, 2007 3:35 pm
Location: Perth

[COM] Re: PRO: Northern Connector | 14km | $1b

#463 Post by drsmith » Mon Jan 25, 2016 12:32 pm

The earth has started to move according to the following announcement from earlier this month,
Two Aboriginal companies have been awarded contracts for work on North-South Corridor projects providing job opportunities for dozens of Aboriginal employees.

Federal Minister for Major Projects Paul Fletcher said Intract Australia - Indigenous contractors - had begun preliminary earth carting works on the $985 million dollar Northern Connector project.

“The Turnbull Government is pleased to be contributing $788 million towards this project which is one of the first to contract out work under the Commonwealth Indigenous Procurement Policy,” Mr Fletcher said.

“Five members of the 10-strong workforce employed by Intract Australia to complete this earth carting work are Aboriginal people.

“The works include delivering up to 1000 tonnes of fill and brine mud each day to fill in embankments across the salt pans up to four metres high before major construction starts in May.”
http://paulfletcher.com.au/media-centre ... -jobs.html

IIRC, material placed over the salt pans had to be allowed to settle for a year before road works proper could begin in that area.

User avatar
drsmith
Legendary Member!
Posts: 513
Joined: Wed Nov 07, 2007 3:35 pm
Location: Perth

[COM] Re: PRO: Northern Connector | 14km | $1b

#464 Post by drsmith » Sat Feb 06, 2016 9:48 am

The Northern Connector project map has been updated.

http://www.infrastructure.sa.gov.au/__d ... t-plan.pdf

At the northern end, the northbound carriageway connection to the Northern Expressway is returned to the northernmost gap under the PWR bridge. This presumably is a (long term) temporary alignment prior to the rail line construction.

The bike path is either nest to or the shoulder of PWR between the Northern Expressway and Waterloo Corner Road.

There's a roundabout connection between Kings Road and Bolivar Road east of PWR.

At the southern end, the tie-in into Salisbury Highway is 3 lanes in each direction.

SBD
Super Size Scraper Poster!
Posts: 2526
Joined: Thu Apr 03, 2014 3:49 pm
Location: Blakeview

[COM] Re: PRO: Northern Connector | 14km | $1b

#465 Post by SBD » Sun Feb 07, 2016 12:37 am

drsmith wrote:The bike path is either nest to or the shoulder of PWR between the Northern Expressway and Waterloo Corner Road.
The shared path must be next to PWR, not on the shoulder itself, as riding northbound would not work on the shoulder of the southbound carriageway. I have not been game to try it in the current configuration, riding on the shoulder next to road trains! It will be interesting to see if they remember to put bike lights and large enough space by the two sets of traffic lights at WCR for groups of cyclists and walkers/runners to cross in both directions without spilling into the roads.

The map has shown that layout for a month or so. some of the property boundaries are quite close to the current carriageway, so there would need to be either a safety fence or some realignment required to make this version of the plan safe for young riders. It was interesting to accompany a friend with his three-year-old on part of the Stuart O'Grady Bikeway recently. It felt like a very safe place for a child to learn to ride in a straight line, and feel like he had gone somewhere. We could not have done this if he could have accidentally drifted onto the road, since following Dad's instructions comes second to enjoying what he is doing.

User avatar
drsmith
Legendary Member!
Posts: 513
Joined: Wed Nov 07, 2007 3:35 pm
Location: Perth

[COM] Re: PRO: Northern Connector | 14km | $1b

#466 Post by drsmith » Sun Feb 07, 2016 2:23 pm

SBD wrote:
drsmith wrote:The bike path is either nest to or the shoulder of PWR between the Northern Expressway and Waterloo Corner Road.
The shared path must be next to PWR, not on the shoulder itself, as riding northbound would not work on the shoulder of the southbound carriageway. I have not been game to try it in the current configuration, riding on the shoulder next to road trains! It will be interesting to see if they remember to put bike lights and large enough space by the two sets of traffic lights at WCR for groups of cyclists and walkers/runners to cross in both directions without spilling into the roads.

The map has shown that layout for a month or so. some of the property boundaries are quite close to the current carriageway, so there would need to be either a safety fence or some realignment required to make this version of the plan safe for young riders. It was interesting to accompany a friend with his three-year-old on part of the Stuart O'Grady Bikeway recently. It felt like a very safe place for a child to learn to ride in a straight line, and feel like he had gone somewhere. We could not have done this if he could have accidentally drifted onto the road, since following Dad's instructions comes second to enjoying what he is doing.
The configuration I was thinking where the pink line was on a road carriageway was northbound on the northbound shoulder and southbound on the southbound shoulder or essentially as is.

I don't think that will fly and there's no indication of a crossing point for northbound at the local road access immediately south of the present PWR bridge over the Northern Expressway.

There's also no hint in the map of work for the carriageway you suggest may be realigned (not highlighted). It may be as you suggest but without the need to move the southbound carriageway.

mawsonguy
High Rise Poster!
Posts: 196
Joined: Fri Dec 20, 2013 8:11 am

[COM] Re: PRO: Northern Connector | 14km | $1b

#467 Post by mawsonguy » Tue Mar 01, 2016 8:02 pm

I was riding my bike along Little Para River tonight and observed a large amount of earhworks going on between the river and the SA Water Waste Treatment plant. Too far south for the Bolivar Interchange but appears to be on the Northern Connector alignment.

User avatar
ChillyPhilly
Super Size Scraper Poster!
Posts: 2588
Joined: Sun Dec 07, 2008 11:35 pm
Location: Kaurna Land.
Contact:

[COM] Re: PRO: Northern Connector | 14km | $1b

#468 Post by ChillyPhilly » Thu Mar 03, 2016 10:22 am

There's minor work going on around the southern vicinity of the salt pans. Can be seen from a relative distance. Excavator in sight.
Our state, our city, our future.

All views expressed on this forum are my own.

User avatar
duke
High Rise Poster!
Posts: 406
Joined: Wed Aug 02, 2006 7:15 pm

[COM] Re: PRO: Northern Connector | 14km | $1b

#469 Post by duke » Mon Apr 18, 2016 4:53 pm

monotonehell wrote:The immediate north of Adelaide area has always suffered from a lack of east-west A roads. Other than Grand Junction and Regency Roads, all others only go part of the way. Everything else is spoke-like from the CBD.
Hopefully the next project will be connecting east-west to the north-south roads.
But given the lack of population growth in the east without major infill, I doubt it will happen.

rev
SA MVP (Most Valued Poster 4000+)
Posts: 6040
Joined: Sat Nov 11, 2006 12:14 pm

[COM] Re: PRO: Northern Connector | 14km | $1b

#470 Post by rev » Mon Apr 18, 2016 7:07 pm

ChillyPhilly wrote:There's minor work going on around the southern vicinity of the salt pans. Can be seen from a relative distance. Excavator in sight.
If it's what I'm thinking of, that's been going on for ages well before any funding announcement for the northern connector.

Goodsy
Legendary Member!
Posts: 1100
Joined: Thu Jul 18, 2013 10:39 am

[COM] Re: PRO: Northern Connector | 14km | $1b

#471 Post by Goodsy » Mon Apr 18, 2016 7:22 pm

rev wrote:
ChillyPhilly wrote:There's minor work going on around the southern vicinity of the salt pans. Can be seen from a relative distance. Excavator in sight.
If it's what I'm thinking of, that's been going on for ages well before any funding announcement for the northern connector.
They're harvesting the salt

victorious80
Gold-Member ;)
Posts: 87
Joined: Fri Jul 31, 2009 8:33 am

[COM] Re: PRO: Northern Connector | 14km | $1b

#472 Post by victorious80 » Tue Apr 19, 2016 8:40 am

They are preloading the site with fill, to ascertain level of subsidence. This will then feed into the road structural design.

Bacon
High Rise Poster!
Posts: 117
Joined: Tue Oct 15, 2013 1:17 pm

[COM] Re: PRO: Northern Connector | 14km | $1b

#473 Post by Bacon » Sun May 01, 2016 9:21 pm

victorious80 wrote:They are preloading the site with fill, to ascertain level of subsidence. This will then feed into the road structural design.
But the tender hasn't even been awarded yet?

victorious80
Gold-Member ;)
Posts: 87
Joined: Fri Jul 31, 2009 8:33 am

[COM] Re: PRO: Northern Connector | 14km | $1b

#474 Post by victorious80 » Mon May 02, 2016 9:01 am

DPTI is delivering the works outside of the main contract as preliminary works. Due to the time required to allow the fill to settle, they couldn't afford to wait until a head contractor was onboard. The same works needed to be done regardless of which tenderer won.

Additionally, DPTI is upgrading the Bolivar / Kings Rd intersection as preliminary works, outside the main contract. The works should be complete in a couple on months, before head contractor hits the site.

mawsonguy
High Rise Poster!
Posts: 196
Joined: Fri Dec 20, 2013 8:11 am

[COM] Re: PRO: Northern Connector | 14km | $1b

#475 Post by mawsonguy » Mon May 02, 2016 8:03 pm

Below is a photo from Google Earth supposedly taken as at 3 March 2016 which shows a large amount of dirt being dumped to the West of Pt Wakefield Rd and to the North of Little Para River. I'm not sure if this is related to the Northern Connector.

Image

Post Reply