#6076 Post by ChillyPhilly » Tue Jul 11, 2023 10:22 pm

Dear CRG Members,

 

I hope you are well. We were wanting to give you an update on a few items related to the project before it is released to the broader public.

 

Local Area Traffic Management

As discussed at the previous CRG meeting on Monday, 19 June 2023, the T2D Project engagement team will be undertaking community consultation on Local Area Traffic Management (LATM) to better understand local access requirements in the project area.

Considering the current T2D Project design, we will be seeking feedback from the local community on:

connecting to the local bike networkdriving through the local street networkwalking across and along South Road and through the nearby local streetsaccessing local bus stops.

Consultation on local access will open tomorrow and close at 5pm, Sunday 6 August 2023.

Face to face LATM community drop-in sessions will be held on the following dates:

 

T2D Community Information Centre, 1194-1196 South Road, Clovelly Park

Tuesday, 25 July 2023 (5pm to 7pm)Saturday, 29 July 2023 (10am to 12pm)

 

Healthy Living Precinct - 16/20 Hindmarsh Ave, Welland

Wednesday, 2 August 2023 (5pm to 7pm)Saturday, 5 August 2023 (10am to 12pm)

 

Local residents and businesses will also be encouraged to provide feedback via the online interactive Social Pinpoint map where they can pin location-specific comments and complete a survey. From first thing tomorrow morning, the online map and survey will be live via the T2D project website.

As you know, refinement will continue to occur as we progress and there has been some minor refinements to the design maps since our meeting with the group on Monday, 19 June 2023.

 

Project Update and Community Consultation Summary Report

For your reference, please see attached the Project Update which will be distributed to all properties within the LATM study area from tomorrow. (To note, it typically takes a few days for properties along the whole alignment to receive the update). The project update includes a QR code that can be scanned to register for the community drop-in sessions noted above.

You will see the project update mentions the Community Consultation Report which summarises the feedback we received between December 2022 and February 2023. This report will also be live on our project website from tomorrow morning. Attached is a copy of the report for you records.

From tomorrow once the website is live, please feel free to share the content and encourage the local community in your area to come and chat with the project team and share their views.

 

Temporary noise walls

At the CRG meeting in June we mentioned that work was underway to look at temporary noise walls. York Avenue, Clovelly Park is the first location planned for a temporary wall.

We have now reached a stage where we would like to seek feedback from the immediate local community (York Avenue, Clovelly Park) about what is planned.

The team will be distributing a flyer to the local residents early this week inviting them to meet with the project team to discuss plans for the temporary noise wall and to seek their feedback.

 

Upcoming business engagement

We will soon be releasing a survey to businesses within the project area to better understand their business needs and requirements and to better understand how we can support local businesses throughout the life of the project.

Thanks for your support and if you have any questions, please feel free to contact the T2D Project engagement team on 1300 951 145 or email [email protected]

Our state, our city, our future.

All views expressed on this forum are my own.

User avatar
ChillyPhilly
Super Size Scraper Poster!
Posts: 2603
Joined: Sun Dec 07, 2008 11:35 pm
Location: Kaurna Land.
Contact:

[U/C] [U/C] [U/C] Re: M2 North-South Motorway

#6077 Post by ChillyPhilly » Tue Jul 11, 2023 10:28 pm

Extra - Project Update.

Image

Image

Image

Image

Our state, our city, our future.

All views expressed on this forum are my own.

User avatar
ChillyPhilly
Super Size Scraper Poster!
Posts: 2603
Joined: Sun Dec 07, 2008 11:35 pm
Location: Kaurna Land.
Contact:

[U/C] Re: M2 North-South Motorway

#6078 Post by ChillyPhilly » Tue Jul 18, 2023 9:20 am

Some tiny extra details appear in the interactive map at https://dit.mysocialpinpoint.com.au/t2d_latm#/

I strongly encourage everyone to leave some feedback about better cycling and pedestrian options as part of this project. It provides a golden opportunity for a new cycling corridor, particularly a north-south one, that does not currently exist in Adelaide.

This is the key update:

Image
Our state, our city, our future.

All views expressed on this forum are my own.

User avatar
whatstheirnamesmom
Gold-Member ;)
Posts: 74
Joined: Fri Jul 13, 2018 11:43 am

[U/C] Re: M2 North-South Motorway

#6079 Post by whatstheirnamesmom » Tue Jul 18, 2023 1:03 pm

I've left a lot of cycling- and pedestrian-related feedback. A couple of points I addressed:
  • Lack of safety/protection for cyclists through intersections
  • Prevalence of slip lanes – a very dangerous conflict point for motor vehicles/cyclists
  • Inclusion of on-road bike lanes on the surface roads, which kids, teens, elderly, most women etc. will not feel safe to use. Would much prefer dedicated cycling paths separated from both motor and pedestrian traffic.
  • Concerned the raised south-bound flyover section across the Torrens near the cemetery will not have a gradient forgiving enough for all cycling users (unsure of height as it was not indicated)
  • The dedicated east-west pedestrian/cycle crossing bridges are generally good (there are 4 now I believe), and – once accounting for major surface intersections – there seems to be an equal distribution of cycling crossing points. The only downside is the non-bridge crossing points are very dangerous to traverse.
  • All arterial intersection approaches are unsafe and the designs should be amended to either reduce speeds to a safe level or hard separation of cyclists and motor traffic should occur
  • It seems arduous for pedestrians (and those cycling who make use of the pedestrian facilities due to not feeling safe to ride on the road, or to ride through the intersections) to travel east-west. In some instances pedestrians will need to cross two lots of slip lanes plus two lots of pedestrian lights to make it to the other side.

User avatar
ChillyPhilly
Super Size Scraper Poster!
Posts: 2603
Joined: Sun Dec 07, 2008 11:35 pm
Location: Kaurna Land.
Contact:

[U/C] Re: M2 North-South Motorway

#6080 Post by ChillyPhilly » Fri Jul 28, 2023 4:11 pm

Another small update to the T2D map, with detail added to the upgrade of Richmond Road.

Image

Triple M also announced that Rhino Crash in Cowandilla (north-west corner of Marion Road/Sir Don Bradman Dr) will be acquired for the upgrade of that intersection.
Our state, our city, our future.

All views expressed on this forum are my own.

rev
SA MVP (Most Valued Poster 4000+)
Posts: 6064
Joined: Sat Nov 11, 2006 12:14 pm

[U/C] Re: M2 North-South Motorway

#6081 Post by rev » Sat Aug 26, 2023 6:31 pm

https://www.t2d.sa.gov.au/news-events?a=1264267

Powering up for tunnelling operations
Published: Thursday, 17 August 2023
Work has started to construct a dedicated electricity substation at Tonsley to power the tunnel boring machines (TBMs) which will excavate the first two tunnels for the T2D Project.

The Tonsley East Substation – to be built, owned and run by SA Power Networks – is being established on the site of a recently demolished former Mitsubishi building fronting South Road and will constitute part of the Project’s Southern Laydown Area.

Work on the new facility – which will supply electricity to the tunnel boring machines (TBMs) and then to the two parallel 4km Southern Tunnels once they are completed in 2030 – is the first construction to occur in direct relation to the T2D Project and will be undertaken by SAPN and its subsidiary Enerven.

Following clearance of the site, and completion of ground investigations and detailed design of the substation, construction began in March 2023 and is expected to take about one year to carry out.

As part of construction of the substation, two 66,000-volt transformers were installed at the Tonsley East Substation in early August 2023.

The substation will be fully operational well ahead of the expected start of TBM works on the Southern Tunnels, with a similar one to be established in the Richmond area to power the TBMs that will build the 2km Northern Tunnels.

The substations are being set up to ensure TBM operations have a reliable and dedicated source of electricity.

The 10.5km T2D Project will enable motorists to have a nine-minute journey from West Hindmarsh to Darlington, and complete the North-South Corridor’s 78km of non-stop motorway between Gawler and Old Noarlunga.

aceman
High Rise Poster!
Posts: 297
Joined: Sat Mar 11, 2006 1:02 am
Location: Adelaide (Hallett Cove)

[U/C] Re: M2 North-South Motorway

#6082 Post by aceman » Wed Sep 27, 2023 8:32 pm

It looks as if preparation works have started for the majors road on/off ramps. some concretes barriers have gone up with areas of ground looking as if they’ve had a grader smooth it off. There’s also some sort of steel structure that looks like it may be used for filling up water trucks for dust suppression over the dry summer months.

User avatar
ChillyPhilly
Super Size Scraper Poster!
Posts: 2603
Joined: Sun Dec 07, 2008 11:35 pm
Location: Kaurna Land.
Contact:

[U/C] Re: M2 North-South Motorway

#6083 Post by ChillyPhilly » Fri Oct 27, 2023 2:11 pm

For what it's worth, the maximum zoom level of the Project Map has been increased, so now you can zoom right in and get a better idea of what properties or infrastructure will be affected.

https://www.t2d.sa.gov.au/planning-design/project-maps
Our state, our city, our future.

All views expressed on this forum are my own.

User avatar
Spotto
Legendary Member!
Posts: 697
Joined: Wed May 15, 2019 9:05 pm

[U/C] Re: M2 North-South Motorway

#6084 Post by Spotto » Sat Oct 28, 2023 4:38 pm

When is the realignment of Raglan Avenue scheduled to be built? It feels like they really should’ve pushed this forward, culling one set of lights in Edwardstown will be welcomed with open arms.

rev
SA MVP (Most Valued Poster 4000+)
Posts: 6064
Joined: Sat Nov 11, 2006 12:14 pm

[U/C] Re: M2 North-South Motorway

#6085 Post by rev » Tue Nov 07, 2023 6:22 pm

The Tonsley hotel is closing 3rd December. Demolition to follow.

RetroGamer87
High Rise Poster!
Posts: 109
Joined: Sat Jun 10, 2017 6:01 pm

[U/C] Re: M2 North-South Motorway

#6086 Post by RetroGamer87 » Wed Nov 08, 2023 8:12 am

Spotto wrote:
Sat Oct 28, 2023 4:38 pm
When is the realignment of Raglan Avenue scheduled to be built? It feels like they really should’ve pushed this forward, culling one set of lights in Edwardstown will be welcomed with open arms.
I had a look on Google Earth history view and it looks like the buildings to the north of the east end of Raglan Avenue were demolished in 2010. Were they demolished in anticipation of the realignment or for some other purpose?

User avatar
ChillyPhilly
Super Size Scraper Poster!
Posts: 2603
Joined: Sun Dec 07, 2008 11:35 pm
Location: Kaurna Land.
Contact:

[U/C] Re: [U/C] Re: M2 North-South Motorway

#6087 Post by ChillyPhilly » Wed Nov 08, 2023 10:27 am

RetroGamer87 wrote:
Spotto wrote:
Sat Oct 28, 2023 4:38 pm
When is the realignment of Raglan Avenue scheduled to be built? It feels like they really should’ve pushed this forward, culling one set of lights in Edwardstown will be welcomed with open arms.
I had a look on Google Earth history view and it looks like the buildings to the north of the east end of Raglan Avenue were demolished in 2010. Were they demolished in anticipation of the realignment or for some other purpose?
I believe this has always been a reserved corridor.
Our state, our city, our future.

All views expressed on this forum are my own.

User avatar
Norman
Donating Member
Donating Member
Posts: 6401
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: M2 North-South Motorway

#6088 Post by Norman » Wed Nov 08, 2023 9:56 pm

RetroGamer87 wrote:
Wed Nov 08, 2023 8:12 am
Spotto wrote:
Sat Oct 28, 2023 4:38 pm
When is the realignment of Raglan Avenue scheduled to be built? It feels like they really should’ve pushed this forward, culling one set of lights in Edwardstown will be welcomed with open arms.
I had a look on Google Earth history view and it looks like the buildings to the north of the east end of Raglan Avenue were demolished in 2010. Were they demolished in anticipation of the realignment or for some other purpose?
This site was the former Hills factory, and was demolished in anticipation of an expansion of the Castle Plaza shopping centre. Those plans then morphed into a residential development, but have stalled since then.

User avatar
ChillyPhilly
Super Size Scraper Poster!
Posts: 2603
Joined: Sun Dec 07, 2008 11:35 pm
Location: Kaurna Land.
Contact:

[U/C] Re: M2 North-South Motorway

#6089 Post by ChillyPhilly » Sat Nov 25, 2023 12:05 am

Our state, our city, our future.

All views expressed on this forum are my own.

Nort
Super Size Scraper Poster!
Posts: 2191
Joined: Tue Feb 09, 2010 2:08 pm

[U/C] Re: M2 North-South Motorway

#6090 Post by Nort » Sat Nov 25, 2023 8:27 am

ChillyPhilly wrote:
Sat Nov 25, 2023 12:05 am
A new video has been released:

https://www.thechronicle.com.au/news/so ... 1700832738
"More open green space for local communities" sign pointing at the park that is going to be significantly shrunk for this development. :lol:

Hopefully that raised long pedestrian path at the James Congdon drive gets a roof or some kind of shade structure on it, otherwise it's gonna be brutal in summer, especially when a lot of what is shown as green areas ends up being gravel.

Post Reply

Who is online

Users browsing this forum: Bing [Bot] and 1 guest