[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Wed Oct 18, 2023 5:21 pm
by Ben
Still no action on site. It’s way too early for a Christmas shutdown. Something seems off…

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Wed Oct 18, 2023 6:01 pm
by abc
they should just lay some asphalt there if the development is stalled

it'd be a great location for a flea market

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Thu Oct 19, 2023 7:13 am
by madelaide
two separate local traders mentioned asbestos was found on site. i guess the logistics of removing that's the focus for now.

[U/C] Re: [SWP] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Thu Oct 19, 2023 7:32 am
by ChillyPhilly
Ben wrote:Still no action on site. It’s way too early for a Christmas shutdown. Something seems off…
I'm not sure a Christmas shutdown is in anyone's interest after this being an original delay last year.

I'm losing a bit of optimism for this.

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Thu Oct 19, 2023 10:29 am
by Prodical
I have a bad feeling that this one is (at best) stalled.

Talking to a Synergy guy on the site opposite last week, he said the rumour was that multiplex cannot build it for the price - a parallel story to Lot 14 and the indigenous museum.

The IEC building at Lot 14 has also stalled + there are v few new proposals for the CBD coming through the SCAP.

Not good.

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Fri Oct 20, 2023 6:11 am
by Mpol02
This is very worrisome. These are also prime spaces and now empty lots. For the central markets this is a disaster if nothing comes from this latest proposal.

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Fri Oct 20, 2023 7:03 pm
by A-Town
The cost of building is astronomical at the moment, so it wouldn't surprise me if the rumours are true.

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Sat Oct 21, 2023 3:04 pm
by ChillyPhilly
I had a chat with Norman about this. We agreed it is possible that some builders are deliberately waiting for the cost of labour/shortages to drop before going ahead.

Short term pain.

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Mon Oct 23, 2023 9:49 am
by notmichaeljfox
Something is happening on site. The trucks said suction.
IMG_0131.jpeg

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Mon Oct 23, 2023 11:30 am
by Pikey
I'd say it's all part of the asbestos removal. I'd also expect some temporary tent/cover structures to be set up too.

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Mon Oct 23, 2023 2:03 pm
by mattblack
Pikey wrote:
Mon Oct 23, 2023 11:30 am
I'd say it's all part of the asbestos removal. I'd also expect some temporary tent/cover structures to be set up too.
I can confirm the removal of 60m2 of asbestos (friable) contaminated soil. Works were slated for completion by 17/10/2023 (where the pump truck is). Further contamination was detected of 80m2 of (friable) contaminated soil, works to be undertaken from 19/10 - 30/11/2023. Aint know one going on that site until they are sure that all asbestos removed unless they can isolate different areas.

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Mon Oct 23, 2023 3:23 pm
by Pikey
mattblack wrote:
Mon Oct 23, 2023 2:03 pm
Pikey wrote:
Mon Oct 23, 2023 11:30 am
I'd say it's all part of the asbestos removal. I'd also expect some temporary tent/cover structures to be set up too.
I can confirm the removal of 60m2 of asbestos (friable) contaminated soil. Works were slated for completion by 17/10/2023 (where the pump truck is). Further contamination was detected of 80m2 of (friable) contaminated soil, works to be undertaken from 19/10 - 30/11/2023. Aint know one going on that site until they are sure that all asbestos removed unless they can isolate different areas.
So hopefully this eases everyone's fears of this site and its future!

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Mon Oct 23, 2023 4:09 pm
by rev
mattblack wrote:
Mon Oct 23, 2023 2:03 pm


I can confirm the removal of 60m2 of asbestos (friable) contaminated soil. Works were slated for completion by 17/10/2023 (where the pump truck is). Further contamination was detected of 80m2 of (friable) contaminated soil, works to be undertaken from 19/10 - 30/11/2023. Aint know one going on that site until they are sure that all asbestos removed unless they can isolate different areas.

Oh come on, I was enjoying watching people take wild guesses.

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Mon Oct 23, 2023 9:26 pm
by mattblack
rev wrote:
Mon Oct 23, 2023 4:09 pm
mattblack wrote:
Mon Oct 23, 2023 2:03 pm


I can confirm the removal of 60m2 of asbestos (friable) contaminated soil. Works were slated for completion by 17/10/2023 (where the pump truck is). Further contamination was detected of 80m2 of (friable) contaminated soil, works to be undertaken from 19/10 - 30/11/2023. Aint know one going on that site until they are sure that all asbestos removed unless they can isolate different areas.

Oh come on, I was enjoying watching people take wild guesses.
Sorry, my apologies for ruining people's fun :banana:

[U/C] Re: Central Market Arcade Redevelopment | 130m | 39 levels

Posted: Tue Oct 24, 2023 8:57 pm
by abc
mattblack wrote:
Mon Oct 23, 2023 9:26 pm
rev wrote:
Mon Oct 23, 2023 4:09 pm
mattblack wrote:
Mon Oct 23, 2023 2:03 pm


I can confirm the removal of 60m2 of asbestos (friable) contaminated soil. Works were slated for completion by 17/10/2023 (where the pump truck is). Further contamination was detected of 80m2 of (friable) contaminated soil, works to be undertaken from 19/10 - 30/11/2023. Aint know one going on that site until they are sure that all asbestos removed unless they can isolate different areas.

Oh come on, I was enjoying watching people take wild guesses.
Sorry, my apologies for ruining people's fun :banana:
what risk mitigation have they done for the general public?

the weather has been dry and windy blowing up all kinds of dust from that site...many people live, shop and work in the area obviously