[U/C] 145-159 King William Street (GPO) | 61m | 16 Levels | Hotel

All high-rise, low-rise and street developments in the Adelaide and North Adelaide areas.
Message
Author
Ben
VIP Member
VIP Member
Posts: 7477
Joined: Mon Dec 19, 2005 11:46 am
Location: Adelaide

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#181 Post by Ben » Wed Jan 27, 2021 9:34 pm

Looks like this is on hold for a bit
S10/4/2018/B
19/01/2021
141-159 King William Street, ADELAIDE SA 5000
Vary previous authorisation works affecting the State Heritage GPO building, being for the construction of a hotel - 16 levels above the ground (incorporating the construction of a 13 level tower above the existing GPO building and including two levels of enclosed plans); the adaptive reuse of the GPO building for a mix of retail and ancillary hotel uses; demolition of the five storey offices to the north of the GPO building; and an infill building over a porte-cochere - VARIATION - Variation to DA 020/A004/18 (V2) - to vary staging of original approval and extend development timeframe. Stage 1 - hotel and adaption of the NE portion of the GPO Building with a 2 year extension to commencement of these works and 5 year completion. Minor variations to building works. Stage 2 - State heritage building and its adaptive reuse for ancillary hotel uses and potential deferral until economic conditions improve (post operation of the hotel - Stage 1)

User avatar
Norman
Donating Member
Donating Member
Posts: 6391
Joined: Sun Mar 25, 2007 1:06 pm

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#182 Post by Norman » Wed Jan 27, 2021 9:38 pm

Makes sense given the current conditions. At least the new central plaza is looking better, with Arbour Lane and the new shops popping up in the middle. The new bar is quite popular for after work drinks.

User avatar
SRW
Donating Member
Donating Member
Posts: 3557
Joined: Fri Jun 08, 2007 9:42 pm
Location: Glenelg

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#183 Post by SRW » Wed Jan 27, 2021 11:36 pm

It'll be a shame if the GPO stands vacant for years. Hopefully they have a mind to activate it, perhaps through rotating tenancies with Renew Adelaide.
Keep Adelaide Weird

Ben
VIP Member
VIP Member
Posts: 7477
Joined: Mon Dec 19, 2005 11:46 am
Location: Adelaide

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#184 Post by Ben » Sun Feb 14, 2021 5:51 pm

Watpac and Marriot signage has gone up all around the site.

Smithy84
Gold-Member ;)
Posts: 96
Joined: Sat Nov 14, 2020 10:18 am

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#185 Post by Smithy84 » Sun Feb 14, 2021 9:49 pm

Is that a bit odd? Mid Jan they apply for a lengthy delay, and then a month later they appear to be about to start?

how good is he
Legendary Member!
Posts: 1233
Joined: Thu Jan 24, 2013 1:26 am

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#186 Post by how good is he » Mon Feb 15, 2021 7:24 am

I agree. Was the extension ever approved? I am pretty sure I read that some councillors were opposed to granting it. Anyone know more?

Neko Neko Peko Peko
Gold-Member ;)
Posts: 62
Joined: Fri May 24, 2019 12:23 am

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#187 Post by Neko Neko Peko Peko » Mon Feb 15, 2021 4:36 pm

[
Ben wrote:
Sun Feb 14, 2021 5:51 pm
Watpac and Marriot signage has gone up all around the site.
Picture of fencing and signage around the site. There is also fencing blocking off Arbor Lane (next to Electra House) with same signage.
Attachments
20210215_161033.jpg

Patrick_27
Super Size Scraper Poster!
Posts: 2436
Joined: Tue Mar 05, 2013 4:41 pm
Location: Adelaide CBD, SA

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#188 Post by Patrick_27 » Mon Feb 15, 2021 8:59 pm

Neko Neko Peko Peko wrote:
Mon Feb 15, 2021 4:36 pm
[
Ben wrote:
Sun Feb 14, 2021 5:51 pm
Watpac and Marriot signage has gone up all around the site.
Picture of fencing and signage around the site. There is also fencing blocking off Arbor Lane (next to Electra House) with same signage.
It could be possible that they're undertaking restoration works and repurposing the building for the short term so that it doesn't sit dormant for however long they intend to delay the primary development. This might have been something encouraged or suggested by planning.

User avatar
AndyWelsh
Legendary Member!
Posts: 748
Joined: Tue Dec 19, 2017 11:44 pm

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#189 Post by AndyWelsh » Tue Feb 23, 2021 10:01 pm

Neko Neko Peko Peko wrote:[
Ben wrote:
Sun Feb 14, 2021 5:51 pm
Watpac and Marriot signage has gone up all around the site.
Picture of fencing and signage around the site. There is also fencing blocking off Arbor Lane (next to Electra House) with same signage.
Had a look around Arbor Lane to King William Street and nothing happening around the new fencing, which you can still just walk past.

Image
Image


Sent from my iPhone using Tapatalk

rev
SA MVP (Most Valued Poster 4000+)
Posts: 6022
Joined: Sat Nov 11, 2006 12:14 pm

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#190 Post by rev » Tue Feb 23, 2021 10:39 pm

Patrick_27 wrote:
Mon Feb 15, 2021 8:59 pm
Neko Neko Peko Peko wrote:
Mon Feb 15, 2021 4:36 pm
[
Ben wrote:
Sun Feb 14, 2021 5:51 pm
Watpac and Marriot signage has gone up all around the site.
Picture of fencing and signage around the site. There is also fencing blocking off Arbor Lane (next to Electra House) with same signage.
It could be possible that they're undertaking restoration works and repurposing the building for the short term so that it doesn't sit dormant for however long they intend to delay the primary development. This might have been something encouraged or suggested by planning.
Bit odd to be putting up scrim signage that includes the hotel tenant for that?

how good is he
Legendary Member!
Posts: 1233
Joined: Thu Jan 24, 2013 1:26 am

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#191 Post by how good is he » Wed Feb 24, 2021 12:16 am

Wondering if the development approval isn’t extended (as requested) they may need to start work by a certain deadline or the approval may lapse altogether?
Last edited by how good is he on Wed Feb 24, 2021 2:56 pm, edited 1 time in total.

User avatar
SRW
Donating Member
Donating Member
Posts: 3557
Joined: Fri Jun 08, 2007 9:42 pm
Location: Glenelg

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#192 Post by SRW » Wed Feb 24, 2021 1:41 pm

Despite the COVID challenges to tourism, Adelaide is still underserved by the big international hotel chains. I wonder if part of their calculation is to get ahead of the proposals by competitors Hyatt Regency and Wyndham.
Keep Adelaide Weird

User avatar
HeapsGood
High Rise Poster!
Posts: 261
Joined: Mon May 10, 2010 10:54 am
Location: At the Adelaide Airport thankfully now not having to use a Dyson Airblade

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#193 Post by HeapsGood » Thu Mar 11, 2021 3:19 pm

From my building admin:

Good afternoon all,

We have received an update from building management confirming that the GPO Hotel development will be commencing soon.

Summary:
 GPO Westin Hotel will be 15 storeys high
 Besix Watpac will be undertaking works with an expected construction delivery frame of 27 months
 Installation of a 3m high acoustic fence / wall on the project site side to minimise any dust and noise and also provide both a physical barrier and security to the construction site.
 Large 35 tonne excavator and various machinery will be used to demolish the 1920 section of the building
 During soft demolition – approx.. 2 months - Truck movements into the site will be via King William St and exit out Exchange Place / Franklin St (lane way between the site and BHP building)
 Electric Luffing Tower crane installed inside of basement excavated area in Telegraph Lane area (between Eleven and Electra House)
 No lifting will ever occur over any neighbouring building or public space (unless protected e.g. King William St covered pedestrian walkways)


For anyone interested, here’s what is proposed > https://www.thehotelconversation.com.au ... 1530683050
*Looks at Dyson Airblade Factory* "I say we take off and nuke the entire site from orbit, it's the only way to be sure"

User avatar
AndyWelsh
Legendary Member!
Posts: 748
Joined: Tue Dec 19, 2017 11:44 pm

[U/C] 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#194 Post by AndyWelsh » Thu Mar 11, 2021 6:19 pm

Great update - thanks HeapsGood.


Sent from my iPhone using Tapatalk

Mpol02
High Rise Poster!
Posts: 425
Joined: Fri Oct 16, 2020 4:06 am

[U/C] Re: 145-159 King William Street (GPO) | 61m | 16 Levels | Westin Hotel

#195 Post by Mpol02 » Thu Mar 11, 2021 7:10 pm

Yeah great update thanks mate.

This development isn’t so much that it’s ugly more that a lot more could be done in this area.
The new BHP building next door did turn out slightly better than expected so I hope this has a high quality finish and ends the same.

Post Reply